China’s first 18 MW offshore wind fleet goes live as Western orders favor low-magnet turbines
Shenzhen-based China General Nuclear’s 2 GW Yangjiang Fanshi complex, 81 km off Guangdong, has entered full operation with 131 turbines, 33 of them 18 MW-class units with 292 m rotors. It is the first deployment of 18 MW offshore machines at scale and is expected to deliver more than 6.6 TWh a year. Chinese offshore turbines of this class run on permanent magnet direct-drive or medium-speed generators. The 18 MW units are Mingyang medium-speed permanent magnet hybrids.
Onshore, China’s build slowed and then re-accelerated. National Energy Administration data released October 26 put installed wind capacity at 700 GW at end-September, up 20.4% year on year, with about 170 GW of wind and solar added in nine months. First-half wind additions of 38.7 GW ran a quarter below a year earlier. State Power Investment Corporation’s (SPIC) second 2026 turbine procurement, about 5.5 GW with candidates named September 10, restocks the pipeline. Beijing-based Goldwind put its external order backlog at 55.1 GW at end-September, 11.0 GW of it overseas. Units of 10 MW and above made up a fifth of its 19 GW of nine-month external sales.